Managing Timelines in Infrastructure Projects

I’m currently overseeing a bridge project that has really highlighted the importance of synchronized timelines, especially when dealing with utilities. We found that involving utility companies earlier in the planning phase saved us weeks of delay. Has anyone else experienced similar outcomes when it comes to timeline management in their projects?

‌⁠‍⁠​‍​‍‌⁠‌​​‍​‍​⁠‍‍​‍​‍‌‍‌⁠‌‍​⁠‌‍‍‍​⁠‌‍​‍​‍​‍⁠​​‍​‍‌‍‍⁠​‍​‍​⁠‍‍​‍​‍‌‍⁠‍‌‍‌‌‌⁠‌⁠‌‌⁠⁠‌⁠‌​‌‍⁠⁠‌⁠​​‌‍‍‌‌‍​⁠​‍​‍​‍⁠​​‍​‍‌‍‍‌‌‍‌​​‍​‍​⁠‍‍​‍​‍‌‍⁠‍‌‍‌‌‌⁠‌⁠​‍​‍​‍⁠​​‍​‍‌‍‌​​‍​‍​⁠‍‍​‍​‍​⁠​‍​⁠​​​⁠​‍​⁠‌‍​⁠​​​⁠‌‍​⁠​‍​⁠‍​​‍​‍​‍⁠​​‍​‍‌‍‍​​‍​‍​⁠‍‍​‍​‍‌​⁠⁠‌‍​⁠‌​⁠‌‌​⁠‍‌⁠​⁠‌‍​‌‌​⁠‌‌​⁠‌​⁠‍‌​⁠‌‍​‍⁠‌‌‍​‌‌⁠​⁠‌​‍‍‌‍‍‍‌⁠‌⁠​‍​‍‌⁠⁠‌​